Brassal Bikeway Cycle Bridges
Scope of Work:
Completion of shop fabrication drawings
Manufacture and pre-assembly
Delivery to site complete ready for install
DWW were contracted to manufacture 3-off 25mtr x 3.5mtr cycle bridges for the new Brassal cycle way. The 3 bridges were identical in design, a fully bolted galvanised truss to support a pre-case concrete panel flooring.
The bridges were fully assembled at our Darra factory before being transported complete to be lifted straight into position by the client. All 3 bridges were landed sucessfully onto pre-installed anchors